Project Description

Based on a 2022 feasibility study, the Education Classrooms building has compromised structural, roof, concrete, and plumbing systems. It is not accessible and cannot be cost-effectively renovated. The Building 67 demolition project includes asbestos abatement and removal, building demolition, as well as stabilization and limited landscaping of the site.

Budget

$1,583,238

Square Footage

22,700

Architect

Design Group

Contractor

Bradbury & Stamm Construction

Funding

Budget: $1,583,238